ResoLex Roundtable round-up: FAC-1 Framework Alliance Contract Lessons

ResoLex Roundtable round-up: FAC-1 Framework Alliance Contract Lessons

Last week, we were delighted to be joined by Professor David Mosey CBE for an update and lessons learned since the launch of the FAC-1 Framework Alliance Contract.

Ed Moore opened the session, commenting that David had first introduced the FAC- 1 Framework to the ResoLex audience at a previous roundtable event in February 2018. It was therefore heartening to see the traction the framework has achieved over the last five years.

David began his presentation by explaining that the FAC-1 is a multi-party framework alliance contract that integrates the procurement and delivery of one or more different projects, with the ability to connect multiple contracts awarded to each collaborative team member. It creates the ability to establish the relationships and systems that the parties wish to use to embed collaborative ways of working, supporting the achievement of improved value, risk management and dispute avoidance.

So far, the contract has been adopted on the procurement of over £100 billion of contracts, ranging from smaller £5 million projects and SME consultant alliances to the £60 billion contractor/ consultant/ supplier procurements of the Crown Commercial Service.

Some of the key features of the FAC-1 contract are as follows:

  • Creates a bridge that integrates multiple project appointments and operates in conjunction with multiple FIDIC, JCT, NEC and PPC forms
  • Allows alliance members to include the client, any additional clients, an in-house or external Alliance Manager and any combination of selected consultants/ contractors/ suppliers/ providers, with the facility to add additional alliance members
  •  Enables the planning and integrating of a successful alliance, setting out why the alliance is being created, and stating agreed objectives, success measures and targets, with agreed incentives if these are achieved and agreed actions if they are not achieved
  • States how work will be awarded to alliance members, under a direct award procedure and/or competitive award procedure and under early standard form orders
  • Describes how the alliance members will seek improved value through shared alliance activities, including a collaborative system for engaging with tier 2 and 3 supply chain members
  • Describes how risks will be managed and disputes avoided, using a shared risk register, core group governance, early warning and options for an independent adviser and alternative approaches to dispute resolution
  • Provides the flexibility to include particular legal requirements and special terms required for any sector and in any jurisdiction.

David highlighted a number of different examples where FAC-1 has been used successfully, and one of the best examples came from the Ministry of Justice.

 

New Prisons complex project alliance

The UK Ministry of Justice (MoJ) created an FAC-1 Alliance to procure their £1.2 billion new prisons programme. The alliance integrates the work of ISG, Kier, Laing O’Rourke and Wates as contractor alliance members, with Mace as alliance manager, and supports their use of BIM and Modern Methods of Construction to agree on optimum designs and strategic relationships with key tier 2 supply chain members.

MoJ report that their FAC-1 new prisons alliance has meant they have been able to use the alliancing process both as a contract form and as the means to structure the relationships. This approach helped to embed the collaborative relationship early, from the alliance launch to the transition through the different phases. Each of the four contractor alliance members nominated representatives from their organisation to sit alongside representatives from the MoJ and its other delivery partners (Mace, WT Partnership and Perfect Circle). Together, they formed the Core Group, establishing strong leadership and trust from the outset.

One of the highly positive outcomes of the use of FAC-1 has been greater cost certainty and cost savings. MoJ reported that these included:

  • Fees for the pre-construction collaboration phase finalised at the tender stage
  • Direct fees (overheads and profit) and staff preliminary rates fixed at the tender stage
  • Projected duration and contract value based on previous prison builds at HMP Five Wells and Glen Parva
  • Pre-construction supply chain collaboration to build up cost certainty and savings by transparent supply chain engagement for key or critical packages on all four prisons i.e., mechanical, electrical, and plumbing engineering, pre-cast concrete, and cell windows and doors.
Final thoughts

The final message from David was that recent evidence suggests that more public sector clients are starting to look at alliancing as a beneficial method of procuring major projects and programmes of construction work. Alliancing does however require a significant shift in both mindset and behaviours, where each of the parties involved is intent on working collaboratively over a prolonged period to achieve win-win gains. In the absence of an agreed set of processes and structured agreements, there is a tendency to revert to short-term transactional behaviours.

The advantage of FAC-1 is that it provides a set of highly flexible mechanisms which are easy to set up, and then provides the programme leadership with the processes needed to create effective relationships.

You can find the round-up from the first FAC-1 roundtable on our website here: https://resolex.com/events/resolex-roundtable-building-a-supply-chain-alliance/

For anyone thinking of using the FAC-1 contract, David has written a handbook which helps clients, contractors and advisors think through some of the practical aspects of implementing the framework. You can purchase it here:  https://www.amazon.co.uk/FAC-1-Framework-Alliance-Contract-Handbook/dp/1913019837

Challenging the Mobilisation Myth: Driving performance through effective Contract Mobilisation – Key takeaways

Challenging the Mobilisation Myth: Driving performance through effective Contract Mobilisation – Key takeaways

On Wednesday the 13th of September, we partnered with the Major Projects Association to host an interactive workshop that challenged the myth of mobilisation – and what an event it was!

We’d like to extend a huge thank you to Liz Lawman, Head of Mobilisation at HS2 (High Speed Two) Ltd and Jonathan Wareham, Project Director at Costain Group PLC for sharing their insights from both a client and contractor perspective. During the workshop, we highlighted some industry best practice and then delved into a session designed to explore the experiences from around the room. We followed Chatham House Rules, but here are a few themes from the afternoon:

  • The movement from traditional transactional relationships that prioritise the lowest tender cost, to a more collaborative relationship that can manage the complexities of major project delivery requires aligned mobilisation
  • Project teams need to understand the need for, and plan to create a cross-functional workstream for the ‘social/behavioural’ elements of major projects, which includes contract mobilisation
  • Ringfence time at the start of a project or programme with senior leaders to co-create with all parties, build the right environment and set the team up with the skills, processes, behaviours and ways of working to develop a collaborative environment
  • Early engagement with the supply chain to co-create solutions is hugely important, and provides even more value when it is part of the procurement approach
  • The team needs to be aligned behind a common purpose from the start. Work to reduce reliance on assumptions that people will work well together

We would like to thank everyone who attended and contributed to what quickly became an incredibly thought-provoking event. We hope to keep the conversation alive and support the development of a more systemised mobilisation framework alongside the MPA and some of the industry experts who joined us.

As a final lesson from the workshop, ‘don’t build the boat after leaving the port!’

ResoLex Roundtable round-up: Behavioural Impact on Productivity

ResoLex Roundtable round-up: Behavioural Impact on Productivity

Last week, we were delighted to welcome three guest speakers from Jacobs to the ResoLex Roundtable: Jessica Ellery, Gail Hunter, and Joshua Weatherley. Jacobs is a full-spectrum professional services firm including consulting, technical, scientific and project delivery with a workforce of about 60,000 people worldwide.

ResoLex Roundtable: Behavioural Impact on Productivity

 

The evening was introduced by our Associate Director, Kelachi Amadi-Echendu, who provided some background to the ResoLex Roundtables and how the event links with our values as a business. Our Chief Executive, Edward Moore then introduced the topic, reminding us that whilst collaboration in itself may be very nice, if it doesn’t improve productivity, one has to question the point! At ResoLex, we see projects as comprising three primary areas of expertise: technical, commercial, and social. We believe that the key elements are interlinked, and the social component is inextricably linked to project performance. During the session, Ed highlighted our model, and expanded on the need to take an integrated approach to the three elements in order to achieve project success.

Jess, Josh and Gail explored the topic through the lens of a live giga project that is in its early stages of delivery in Saudi Arabia. A perspective offered was that perhaps the scale and longevity of such programs offered the chance to truly embed an effective, collaborative social system, even more so than the opportunity we have in the mega-project environment. The presentation began with a poignant safety moment, and then an introduction to four immense projects in the Neom region of Saudi Arabia. Each of these projects are hugely ambitious, the most dramatic being The Line. The Line is a revolution for urban living, which according to the plans will be 500m tall, 200 meters wide and a staggering 170km in length. Whilst a project of this scale is fascinating in itself, the evening’s platform served as the backdrop to a much broader discussion around the challenges of working in such a complex programme environment. Throughout the session, Josh and Gail prompted the audience with a range of engaging questions and themes designed to stimulate debate (a dangerous thing to do with a ResoLex audience!).

ResoLex Roundtable: Behavioural Impact on Productivity

The presentation identified the challenges created by the multiple interfaces that must be managed by the teams and explained that this becomes exponentially more difficult to cope with as size and scale increase, supporting the initial introduction and highlighting the need to therefore factor in behaviours when setting the project strategy. This stimulated a lengthy discussion in the room around the more nebulous concepts of leadership and project culture, there was a common agreement that paying attention to these areas early in the programme is a critical success factor. It was also noted that one of the reasons for the poor performance of mega projects, in general, is the lack of ability for many project leaders to scale up from large projects, and when faced with high levels of complexity, they tend to fall back on simplistic solutions which inevitably fail in more complex and challenging environments.

So, what are the conclusions from the evening’s discussion? Here are our top five takeaways:

  • There is a need to ‘operationalise’ collaborative intent. In other words, major projects (and especially giga projects) need to focus on establishing the policies and processes that will embed the principles of collaborative ways of working throughout the programme, rather than limiting the discussion to senior management.
  • Focus on the active steps needed to build a positive culture, avoiding the default tendency to revert to transactional behaviours as soon as the project comes under pressure.
  • The risk management process needs to acknowledge behavioural risk and recognise that effective inter-team relationships are both a risk and an opportunity.
  • Relationship management plans should be a compulsory part of the early planning process and should focus on identifying the critical interfaces that need to be mapped and managed.
  • Project leaders need to be trained specifically in the practical tools and techniques that will enable them to make the right decisions when working in highly ambiguous and complex environments.

The session closed with reference to the work of Edgar Schein, and his observation that for successful teams, people need to build ‘Level 2 relationships’ with their colleagues. This level of relationship is where we know enough about the people we work with on a regular basis to be able to see them as human beings, rather than just human ‘resources’, who carry out a functional role.

Overall, it was another stimulating and educational evening, with a wide range of views and opinions. As we see projects and programmes becoming ever more ambitious in their scale and desired outcome, the session is a reminder (should we need it!) that planning, setting up and mobilising for success from the start makes life considerably easier for the teams trying to deliver downstream.

If you’d like to join our next Roundtable, please keep an eye on our events page or sign up for our LinkedIn events newsletter.

UK Construction Week 2023: Culture Change

UK Construction Week 2023: Culture Change

Yesterday, we visited ExCeL London for the first day of UK Construction Week 2023. The theme this year focused on the importance of ‘culture change’ within the industry and was celebrated with a Culture Change Hub, a new addition to the Construction Week programme. Sessions at the Culture Change Hub were delivered by a diverse range of speakers and panellists, covering topics including equality, diversity and inclusion, mental health and attracting new entrants to the industry.

It was great to see so many people coming together to challenge the status quo, articulate the cultural barriers within the industry and highlight the need for change. Below are some of our key takeaways from the day.

Culture change: What does it mean for the construction industry?

Panellists:

  • George Clarke, Architect, television presenter, lecturer and writer – Channel 4, MOBIE (Facilitator)
  • Mike Pitts, Deputy Challenge Director – Transforming Construction – Innovate UK
  • Nikita Mikhailov, Personality Psychologist – PsyPub
  • Amit Oberoi, Executive Chairman – Considerate Constructors Scheme
  • Bijal Mehta, Associate – Marchini Curran Associates

The panel members as part of this seminar identified that we are experiencing an important shift in language. We are moving away from a focus purely on construction, towards the ‘built environment’ as a descriptor for the activities that organisations across the industry are involved in and contribute to. This is a more inclusive way to describe the industry, both allowing room to include designers, clients, and those with boots on the ground delivering the projects and encompassing the societal and environmental impacts of all aspects of what we do as an industry.

The discussion moved to the realm of mega projects, with reflections that they often draw negative attention in the media, reporting is often focused on problems, delays and over-expenditure, with limited mention of the positive impacts, particularly for local communities. The panellists all agreed on the power of stories and narrative, and endorsed a need for positive stories to be spread about the positive transformation that these major programmes deliver.

Culture Change panel

There was a consensus that there is still a need for a huge change in culture and more importantly mindset. The culture of the industry needs to be more inclusive and better at embracing diverse thinking. Discussions on confirmation bias and tribal tendencies reminded us that, as individuals, we like to stick with groups of people who support our thinking and may therefore struggle to harness the benefit of our differences. Actively listening to those who may challenge our thinking will encourage differing perspectives, allowing us to have a better understanding and hopefully, avoid biased thinking.

Cultural change: how?
While it is great to see many people highlighting the importance of cultural change, we need to look at how and more importantly, why?

There is a growing awareness of the impact that culture has on the success of any large group of people trying to work together. The limited research that has been done tends to focus on culture change in existing businesses and institutions but seldom project delivery teams.

Not only will this encourage diverse thinking but a positive and healthy culture will drive increased performance and staff retention.

There is no simple blueprint for how to approach culture on a project but we did start to address the topic in an article that looks at the culture within the project environment and explores how you can build and sustain the desired culture in the project environment: https://resolex.com/news-insight/culture-in-the-project-environment/

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Using a ‘Collaboration Workstream’ to improve project performance

Using a ‘Collaboration Workstream’ to improve project performance

Projects often start with positive intentions, especially if you hold a good kick-off workshop which generates lots of ideas and action plans, and the team leave the event feeling energised and hopeful. Pretty soon, however, the reality of delivery kicks in and all the plans that would have embedded collaborative ways of working drift to the periphery of the agenda. So how do you keep the momentum going after the initial workshop is over? The best mechanism we have found is to establish a collaboration workstream.

A workstream is essentially a cluster of tasks that need to be completed to achieve a particular outcome within the project. The point of the collaboration workstream is to follow up on the actions and initiatives that the leadership team know are important, but are often otherwise displaced by the urgent issues that typically dominate their agenda. To give an example, the following list of questions emerged from the output of a recent project kick-off workshop:

  1. How do we establish a culture of ‘collaborative delivery’ throughout the project so that everyone understands the positive behaviours?
  2. What are the teams’ non-financial objectives and what are activities that will support their achievement?
  3. What actions are needed to develop a well-considered Relationship Management Plan?
  4. How does the project leadership monitor and measure the relationships between the key parties involved?
  5. How do we establish a communication strategy that emphasises the underlying narratives that will support a collaborative culture?
  6. What is the collaborative maturity of the teams and what training is needed to improve their collaborative skills?
  7. Where are the potential areas of disagreement/dispute that potentially lie ahead and how do we prepare the teams to avoid or resolve them?
  8. How do we define collaborative ways of working and how do we communicate them to everyone working on the project?

Each of these questions is a component of the overall delivery strategy that will require different levels of attention throughout the project lifecycle. As you can see, there is a lot to do, and so the tasks that arise from the discussion need to be resourced, organised and managed. It, therefore, makes sense to form a ‘Collaboration Workstream Steering Group’ that meets at regular intervals to oversee the progress. We recommend that the membership of the group should be no more than 5 to 6 people.  Within this group,  there must be a senior project manager or leader and ideally a collaborative specialist. The remainder of the group should be selected from individuals senior enough to ensure decisions are acted upon.

The other critical success factor is to identify and set up metrics that are reported to the project leadership team regularly. Collaborative metrics might include:

  • Culture of trust and openness
  • Clarity of delivery strategy
  • Alignment of teams to the common goal
  • Effective communication
  • Effective meetings
  • Information sharing
  • One team ethos

Throughout the programme, one would expect to see these metrics move positively and negatively depending upon periods of pressure. We have found that reporting the trends regularly keeps the people element of the programme higher up on the leadership team agenda, prompting actions that can then be managed by the ’Collaboration Steering Group.

Collaborative delivery is as much a philosophy as it is a series of activities, but to be effective it must sit at the heart of a project or programme. By establishing a collaboration workstream, the management team is creating the facility to ensure the behaviours needed to achieve success are embedded into the team’s culture.